1)
list three widely used tyres of
a wiring sysytem
b wiring enclosure
2)
when making an area safe to work in
a list 3 procedures to be taken before commencing work
b describe the permit to work procedure
3)
when carrying out large contracts
a list three parties likely to be concerned
b state the perpose of a site record
4)describe the use of the following in monitoring the progress of a contract
a a bar chart
b a site diary
c variation order
5) with the reference to the application and the use of residual current devices (RCD)
a list three situations where RCD protection is required
b state the primary function of an RCD
C describe the term nuisance tripping
6)
a explain briefly the importance of a verification of test instruments before performing tests on an electrical installation.
b state the purpose of each of the following types of test instrument
i) insulation resistance tester
ii) tong tester
iii) pscc tester
iv) low ohms meter
7) a 10kW230v shower is supplied using PVC/PVC multicore cable clipped direct to the surface over a distance of 15m. the circuit is protected by a BSEN 60898 type C circuit breaker , the ambient temperature is 25 deg C
determine
a installation method
b design current
c circuit breaker rating
d correction factor
e minimum cable size
f voltage drop
8)
identify three items to be checked during the initial inspection progress for -
a steel conduit
b steel trunking
9)
when completing addititons to a circuit such as an extra socket
a state the type of certificate to be used
b list three item of information that need to be entered on the form
c state to who the form should be given
10)
describe breifly the purpose and types of information which relate to the electrical installation of the following types of drawing
a site plan
b block diagram
c circuit diagram
11)
a explain the importance of coordinating electrical installation contracts with other trades
b describe one example where joiners/ carpenters may be held up due to lack of coordination with electricians working on the same site
c describe one example where plasters may be held up due to lack of coordination with electricians working on the same site
12)
a with the aid of a sketch , show how a 230v single phase supply and a 400v three phase supply is achieved within a sub-station using a transformer with delta connectedn11kV primary windings and the star connected secondary windings
4 marks
b state two reasons for balancing the loads across a three phase four wire system
2 marks